There is a lot going on at NUI Galway at the moment. Amongst the various construction projects that are either underway or about to commence is the €20 million Clinical Research and Translational Research Facility. This project is located within the grounds of the University Hospital Galway campus.
BAM was awarded the contract to construct the five-storey building (gross floor area 5,345m²) which is directly adjacent to the University’s Clinical Science Institute, UHG’s Critical Care Facilities, Ward Accommodation Block and the Maternity Wards. Construction is expected to be completed in the first quarter of 2015 and some 125 construction jobs will be created at the project’s peak. The architectural firm undertaking the project is Reddy Architecture & Urbanism, the structural engineers are Barrett Mahoney and services engineering is provided by Homan O’Brien.

Padraig Walsh at BAM is the Contract Manager on the project while Luke Gibbons is the Project Director. “The new project is right in the heart of the hospital campus so it’s a very tight site with major logistical challenges involving getting materials in and out,” says Luke. “It involves a lot of service diversion and rerouting of roads prior to the main construction starting. In conjunction with the HSE and NUI Galway, a lot of detailed planning is going into the project to ensure the works don’t impact on the daily operation of the campus.” The BAM team has to make sure traffic flow is maintained on the hospital ring road while works are taking place; priority is given to emergency vehicles at all times and this issue is dealt with by the site specific traffic management plan. “We’re using a precast concrete frame so that will decrease the number of deliveries to the site during this phase.” Works around live services are also an issue as the existing hospital campus contains multiple service utilities both above and below ground. According to Luke Gibbons, “Other issues we need to be aware of are the risk of Aspergillus infection to patients from the work activities and noise levels from the project. The scheduling of tie-ins to existing hospital infrastructure is dependent on close co-operation with the HSE as well.”
The timelines on this project are especially tight; the construction will be undertaken in two phases. During the initial phase, a temporary access road will be built through the site to allow for the de-commissioning, diversion and installation of new service provisions like water mains, oxygen, storm and foul sewers, natural gas, medical gas, electrical and data cabling. A new permanent access road will also be constructed during this phase, which will link the rear of the Maternity Ward Block with the campus ring road network. When this road is finished and handed over to the client, phase two works will commence which will be the actual construction of the building over the following year. Associated external works inside the phase 2 site boundary and links to the existing CSI and Ward Block 2A Buildings will also be actioned within this second phase.

NUI Galway is known as one of the more progressive universities with an excellent track record in securing funding and expanding their campus. “Strategically, the university has been a very important client for us. They’re continually developing the campus so it’s great to be involved and get a share of the work that they’re involved in,” says Pádraig Walsh.
BAM is also about to commence another project on the UHG campus – the Adult Acute Mental Health Hospital. Consisting of the relocation of the existing Acute Adult Mental Health Unit (AAMHU) at University Hospital Galway (UHG), to a newly constructed two-storey 50 bed facility, the project is a public works contract designed by the contractor with a 90 week construction programme.
The Adult Acute Mental Health Facility incorporates an out-patient department on the site of an existing staff car park within the grounds of UHG. The new AAMHU will have a gross internal floor area of 4741.3m2 including a rooftop plant room to the western end of the plan, together with associated site works. In total, 170 existing car parking spaces will be displaced arising out of the development; a new two storey car park consisting of 238 spaces together with associated site works will be built in the existing car park to the north east of the helipad on the new hospital ring road. The decommissioning of a fuel tank and LPG facility also form part of this contract on the car park site. BAM will also be responsible for the relocation of the ambulance service. The AAMHU site involves work adjacent to electrical HV services and a sewerage pumping station.
Again, the €15 million project will be divided into two phases; the first phase consists of the construction of a double storey deck car park of 238 car parking spaces together with associated site works. Temporary ambulance parking, widening of the road and the provision of a permanent path, the construction of the double storey car park and the re-surfacing of the existing car park make up the first phase. Phase 2 consists of the construction of the two storey 50 bed Facility.
Similar to the CRF-TRF, a major challenge with this build is ensuring that hospital traffic is not hampered in any way during the construction. Out-of-hours working will be a necessity, especially in the early phase of the project when relocation of services will be undertaken. Life safety systems such as medical gases will also have to be relocated without disrupting in any way the function of the live hospital. In addition, live electrical ring main services will also have to be relocated without causing disruption. “It’s a very tight site so in order to maintain the excellent working relations we have with both the HSE and neighbour’s, we ensure that we liaise with them regularly and inform them of any future plans which may impact on them,” says Padraig Walsh. The BAM team must be vigilant when it comes to keeping noise levels at a minimum so as not to disturb hospital patients and staff and particular care will be paid to ensure that airborne spores are not allowed contaminate the live hospital.
The completion of these two projects at NUI Galway/UHG coupled with the existing Engineering Building and the Bank of Ireland extension (on the NUI Galway Campus) will further cement BAM’s reputation in the West.
The BAM brand and the ability of the company to carry out large scale multidisciplinary projects ensures that they continue to maintain a strong position in this current market both regionally and nationally.